Import PTI Subsystems Dialog
If there is no ambiguity in the import file, new injection groups will be created with the defined subsystem names without further prompts to the user. No ambiguity means that either participation points are defined for buses that have either load or generation but not both or that no participation points are defined and that injection group participation points will be defined based on the maximum generation for each on-line generator in the defined subsystem. If participation points are defined without ambiguity, each participation point will be assigned to either the load or generation at the bus split equally across all loads or generators at the bus.
If there is ambiguity in defined participation points, the Insert PTI Subsystems into Injection Groups Dialog will be displayed. This dialog prompts the user how participation points should be handled for buses with both load and generation or buses with no load or generation.
Buses with Load and Generation
This option allows the user to select how a defined participation point will be assigned if the participation point bus has both load and generation.
Assign Participation Point to Generation
The participation point will be assigned to generation at the bus. The participation point will be split equally across all generators, either on-line or off-line, at the bus.
Assign Participation Point to Load
The participation point will be assigned to load at the bus. The participation point will be split equally across all loads, either connected or not, at the bus.
Buses with No Load or Generation
This option allows the user to select how a defined participation point will be assigned if the participation point bus has no load or generation.
Ignore Participation Point
The participation point will be ignored.
Add Equivalent Load (closed load with ID=’99’ and 0 MW and 0 Mvar) and Assign Participation Point to this Load
This option adds a connected load at the participation point bus with ID=’99’ and 0 MW and 0 Mvar. The participation point is then assigned to this new load.
For each subsystem that is read that is found to have ambiguity in the defined participation points, the Insert PTI Subsystems into Injection Groups Dialog will be displayed unless the user selects Same Options for All Subsystems (Do not prompt again).